Volume 9 Week 19

Friday, July 30


 

Updated July 11

Updated June 8


Click on image
for more info

 

 

 

   

 

(Updated 7:30 a.m., Dec. 16)
Hydro One officials deliver update on local service improvements
By Fred Sherwin
Orléans Online

It's been exactly one year since a pair of blackouts left local Hydro One customers shivering in the cold.

The first, on Dec. 3, was caused by a defective conductor on the high voltage line which runs through Orléans from the Ottawa River to the main transformer station on Hawthorne Road. Some 12,000 resident were without hydro service for up to eight hours.

The second power outage happened two weeks later on Dec. 23 when a faulty regulator at the Wilhaven Distribution Centre on O’Toole Road failed resulting in a four hour interruption in service during the early morning hours.

When service was restored, it caused a power surge that fried the electronics in a number of furnaces which left some homes without heat for as long as two days.

While both of the incidents were caused by unforeseen events, that fact didn’t ease the frustration felt by the residents who crowded into the Orleans Client Service Centre for a public meeting on March 17.

At the meeting, residents were told that Hydro One was in the process of investing millions of dollars in upgrading local infrastructure which would result in fewer outrages and short interruptions.

At the time, the Hydro One officials promised to hold a follow-up meeting in the fall to give residents an update on the work that had been done.

That meeting was held on Dec. 10 at the Orléans Legion. As an indication that hydro service may no long up be a burning issue, only four people showed up for the meeting.

Those people who did show up heard that service disruptions are way down since last spring.

Since March 17 there have been nine unplanned power disruptions and 20 planned disruptions. Three power outages in the area were caused by lightning strikes, affecting 19,000 customers for a duration not more than three minutes. Three additional outrages were caused by equipment failures, the largest of which affected 2,160 for two hours and 15 minutes, and two smaller disruptions were caused by motor vehicle accidents.

Finally, there were 20 planned outrages to allow for equipment replacement and routine maintenance. The planned outrages usually lasted less than two hours and were scheduled to take place in the early morning hours.

Among the many upgrades that have been made are an increase in capacity at both the Wilhaven and Navan distribution centres and improvements in feeder reach and tie capability which will enable Hydro One to switch to an alternate power supply in the event of an unplanned outage.

To further improve reliability, the hydro utility is the process of installing a “smart source” automated monitoring system at the Wilhaven DS that will allow technicians to restore service by remote control rather than having to drive out to the site which takes time.

(This story was made possible thanks to the generous support of our local business partners.)

 

Return to top

Return to Front Page

 

 

   

 

Updated July 28

Updated March 12

Click on image



Click on image



 

 

 


Orléans Online © 2001-2009 Sherwin Publishing